TY - CONF TI - Improving Non-Repetitive Takt Production With Visual Management C1 - Lima, Peru C3 - Proc. 29th Annual Conference of the International Group for Lean Construction (IGLC) SP - 797 EP - 806 PY - 2021 DO - 10.24928/2021/0195 AU - Grönvall, Max AU - Ahoste, Henri AU - Lehtovaara, Joonas AU - Reinbold, Ana AU - Seppänen, Olli AD - Development Engineer, Skanska Oy, Finland, max.gronvall@skanska.fi, orcid.org/0000-0001-8635- 128X AD - Production Engineer, Skanska Oy, Finland, henri.ahoste@skanska.fi, orcid.org/0000-0002-5932-375 AD - Doctoral Candidate, Department of Civil Engineering, Aalto University, Finland, Joonas.lehtovaara@aalto.fi, orcid.org/0000-0002-4761-3811 AD - Doctoral Candidate, Department of Civil Engineering, Aalto University, Finland, ana.reinbold@aalto.fi, orcid.org/0000-0002-7774-7984 AD - Associate Professor, Department of Civil Engineering, Aalto University, Finland, olli.seppanen@aalto.fi, orcid.org/0000-0002-2008-5924 AB - Takt production is gaining increasing visibility in the construction industry. To further improve the current takt production practices, visual management tools could offer improved efficiency in the production control phase. However, the effects of visual management in takt control setting have not yet received much attention in research. This study aimed to investigate the effects of various visual tools in a takt production setting to gain knowledge on how these tools could aid takt control efficiency. The research utilized a design science research approach to create visual management tools and iterate them based on feedback. Interviews, site observation, and takt progress tracking were used to evaluate the implemented tools. The findings indicate that workers on site want to be more aware of the production plan, and information helps them to work in the right location at the right time. To help workers, visual management tools need to recognizable, explicit, and contain correct and up-to-date information. However, there are cultural issues related to implementation, especially on the need for information going through foremen to crews. KW - Visual management KW - takt control KW - lean construction KW - takt production KW - production planning and control. PB - T2 - Proc. 29th Annual Conference of the International Group for Lean Construction (IGLC) DA - 2021/07/14 CY - Lima, Peru L1 - http://iglc.net/Papers/Details/1931/pdf L2 - http://iglc.net/Papers/Details/1931 N1 - Export Date: 29 April 2024 DB - IGLC.net DP - IGLC LA - English ER -