TY - CONF TI - Implementing PPC in Korea’s Construction Industry AU - Lim, Chul-woo AU - Yu, Jung-ho AU - Kim, Chang-duk AD - Graduate student, Department of Architecture Engineering, Kwangwoon University, 447-1 Wolgye-Dong, Nowon-Ku, Seoul, Korea FAX +82-2-942-7101 (icw34@kw.ac.kr) AD - Professor, Department of Architecture Engineering, Kwangwoon University, 447-1 Wolgye-Dong, Nowon-Ku, Seoul, Korea FAX +82-2-942-7101 (myazure@kw.ac.kr) AD - Professor, Department of Architecture Engineering, Kwangwoon University, 447-1 Wolgye-Dong, Nowon-Ku, Seoul, Korea FAX +82-2-942-7101 (stpkim@kw.ac.kr) PY - 2006 DA - 2006/01/01 T2 - 14th Annual Conference of the International Group for Lean Construction C3 - 14th Annual Conference of the International Group for Lean Construction CY - Santiago, Chile AB - Developed by the Lean Construction Institute, the Last Planner ® System (LPS) consists of four steps: Master Schedule, Phase Schedule, Lookahead Planning, and Weekly Work Plan. This paper focuses on the process of measuring the Percentage of Plan Completed (PPC) at the Weekly Work Plan stage. PPC refers to the percentage of weekly assignments completed. The results of research on the use of PPC in many other countries confirm the benefits of using PPC. In Korea’s construction industry, however, the concept of PPC is still relatively new. This paper analyzes the cases of PPC application in other countries and compares it with the production control system in Korea’s construction industry. The results of this research are expected to serve as the basis for the institutionalization of the PPC implementation process in Korea. KW - Last Planner System KW - Lookahead Plan KW - Weekly Work Plan KW - PPC KW - Time Management L1 - https://www.iglc.net/papers/details/436/pdf UR - https://www.iglc.net/papers/details/436 DB - IGLC.net LA - English N1 - Export date: 04 October 2026 ER -