Implementation of Progress Monitoring Dashboard Based on Last Planner System on Pavement Work: a Case Study of Bayung Lencir – Tempino Section 3 Toll Road Construction
- Director of Operation I, PT Hutama Karya (Persero), Jakarta, Indonesia, agung.fajarwanto@hutamakarya.com
- Executive Vice President of Civil Construction Division, PT Hutama Karya (Persero), Jakarta, Indonesia, rizky.agung@hutamakarya.com, orcid.org/0009-0000-4174-8945
- Executive Vice President of Engineering & Information Technology Division, PT Hutama Karya (Persero), Jakarta, Indonesia, aji.sentosa@hutamakarya.com, orcid.org/0009-0001-5801-6262
- Vice President of Engineering, Civil Construction Division, PT Hutama Karya (Persero), Jakarta, Indonesia, akhyaarul.azzaqy@hutamakarya.com
- Vice President of Digital Construction, Engineering & Information Technology Division, PT Hutama Karya (Persero), Jakarta, Indonesia, amy.rachmadhani@hutamakarya.com, orcid.org/0009-0006-7600-6064
- Assistant Manager of Construction Department, Civil Construction Division, PT Hutama Karya (Persero), Jakarta, Indonesia, ariel.winfried@hutamakarya.com
- Officer of Engineering Department, Civil Construction Division, PT Hutama Karya (Persero), nadlirulwachid@gmail.com
- Senior Analyst of Digital Construction, Engineering & Information Technology Division, PT Hutama Karya (Persero), Jakarta, Indonesia, dwi.nugroho@hutamakarya.com
- Analyst of Digital Construction, Engineering & Information Technology Division, PT Hutama Karya (Persero), Jakarta, Indonesia, audy.aditriananda@hutamakarya.com
- Executive Vice President of Human Capital Division, PT Hutama Karya (Persero), Jakarta, Indonesia, mardiansyah@hutamakarya.com
https://doi.org/10.24928/2025/0246
Abstract
The integration of digital progress monitoring tools in construction enhances workflow transparency and real-time decision-making. This study evaluates the application of a collaborative digital dashboard in the Bayung Lencir–Tempino Section 3 Toll Road project, focusing on its alignment with the Last Planner System (LPS). Using a case study approach and Fishbone Diagram analysis, key limitations in progress tracking, constraint management, and stakeholder collaboration were identified. While the dashboard improved milestone tracking and data transparency, challenges remained in manual data entry inconsistencies and identifying and addressing constraints before they impact the progress.
Findings highlight the need for predictive tracking, structured commitment planning, and automated constraint removal to enhance LPS integration. Recommendations include improving dashboard automation, embedding structured feedback loops, and integrating predictive analytics to support continuous improvement in Lean-based infrastructure projects. This study contributes to Lean Construction knowledge by demonstrating how digital monitoring systems can better support LPS implementation, leading to more effective planning, execution, and resource management.
Keywords
- Road Construction
- Project Management
- Last Planner System
- Progress Monitoring Dashboard
- Respect for People.
Cite this paper
APA 7th edition
Fajarwanto, A., Saputra, R. A., Sentosa, G. A., Azzaqy, A. U., Widyastuti, A. R., Winfried, A., Wachid, N., Nugroho, D., Aditrianandaand, A., & Mardiansyah, B. (2025). Implementation of Progress Monitoring Dashboard Based on Last Planner System on Pavement Work: a Case Study of Bayung Lencir – Tempino Section 3 Toll Road Construction. In O. Seppänen, L. Koskela, & K. Murata (Eds.), Proceedings of the 33rd Annual Conference of the International Group for Lean Construction (IGLC 33) (pp. 529–539). https://doi.org/10.24928/2025/0246
Shortened reference for IGLC papers
Fajarwanto, A., Saputra, R. A., Sentosa, G. A., Azzaqy, A. U., Widyastuti, A. R., Winfried, A., Wachid, N., Nugroho, D., Aditrianandaand, A., & Mardiansyah, B. (2025). Implementation of Progress Monitoring Dashboard Based on Last Planner System on Pavement Work: a Case Study of Bayung Lencir – Tempino Section 3 Toll Road Construction. IGLC33. https://doi.org/10.24928/2025/0246