Buffer Management in Takt Planning – An Overview of Buffers in Takt Systems
- Lean Expert, BMW AG Munich, Germany, +49-721-695-245, janosch.dlouhy@kit.edu
- Research Fellow, Karlsruhe Institute of Technology, Germany, +49-721-608-44124, marco.binninger@kit.edu
- Professor, Karlsruhe Institute of Technology, Germany, +49-721-608-42646, shervin.haghsheno@kit.edu
https://doi.org/10.24928/2019/0226
Abstract
Takt Planning and Takt Control (TPTC) as a method for construction has the potential to reduce construction time in relation to normal scheduling without the increase of manpower. This leads to the question: what changes with the use of Takt planning? One theory is that Takt planning is using buffers more effectively than other schedule and planning methods. This paper provides an overview of the various buffers in Takt planning and describes how they can be used.
Keywords
- Lean construction
- buffer management
- buffer
- takt
- takt planning.
Cite this paper
APA 7th edition
Dlouhy, J., Binninger, M., & Haghsheno, S. (2019). Buffer Management in Takt Planning – An Overview of Buffers in Takt Systems. In Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC) (pp. 429–440). https://doi.org/10.24928/2019/0226
Shortened reference for IGLC papers
Dlouhy, J., Binninger, M., & Haghsheno, S. (2019). Buffer Management in Takt Planning – An Overview of Buffers in Takt Systems. IGLC27. https://doi.org/10.24928/2019/0226